2015-07-09 PLTU 4 BBL (2X16.5MW) Power Plant #1 Unit Performance Test Successful Completed

Today July 8,2015 is a special day for The PLTU 4 BBL (2X16.5MW) Power Plant, as the #1 unit performance test completed at 10:22am successfully, the whole power plant is under the celebration!

Based on confirmed performance test procedures, the SOMEC site commissioning team executed every performance test items successfully through two weeks hard working by overcoming every kind of difficulties. The performance test including: the auxiliary power consumption and public, ESP efficiency, Boiler and Turbine MCR twice, 50%MCR, 75%MCR, HP heater cut, 105%BMCR etc. various condition test and data acquisition.
The performance test is recognized by all parties which also provides and accumulates the experience for the next step #2 unit performance tests.
The complete of performance test is another important millstone for the project, after which the 1# unit will get into the stage of COD. This successful will encourage the site commissioning team to complete the #2 unit of PLTU 4 BBL (2X16.5MW) Power Plant.