2015-04-08 PLTU 4 BBL (2x16.5MW) #1 Unit Load Rejection Successful Completed

April 5, 2015 was another special day for the PLTU 4 BBL (2x16.5MW) Power Plant, as the load rejection tests with 50% & 100% load are complete successfully at 11:54 and 14:58 coordination with the local power sector.

Load rejection test is part of commissioning test for power plant to check whether the unit can withstand the sudden loss of load and keep itself stable house-load. The successful completion of the load test marks the #1 unit turbine governor system well and the unit will forward to the RR Test.